Watch the construction on the Rapid City Correctional Facility progress:
Groundbreaking ceremony October 16, 2023
Secretary of Corrections Kellie Wasko.
Andy Scull of Scull Construction.
Project stakeholders.
DOC staff members.
June 2024
Crews begin with the dirt work.
September 2024
Ground level views taken 9/4/2024.
Aerial view from west to east 9/11/2024.
Aerial view from east to west 9/11/2024.
October 2024
A view of the eastside of the Administration building (left) and the Housing Unit 2 building (right) taken on October 16, 2024, one year after the groundbreaking.
A view of the Programs and Services building.
A view of one of the utility trenches for electrical conduit.
The first of the precast walls go up for Housing Unit 3 as of October 31, 2024.
November 2024
The Programs and Services building east to west on 11/13/2024.
Precast walls for Housing Unit 1 11/13/2024.
Housing Unit 3 on 11/13/2024.
Roof bar joists on Housing Unit 3 11/13/2024.
Precast walls on the three housing units 11/27/2024.
Plumbing and electric work in a housing unit 11/27/2024.
The roof structure in one of the housing units11/27/2024.
Foundation work for the Programs and Services building 11/27/2024.
December 2024
The last of the precast walls are being erected for the administration building.
January 2025
January 8, 2025
January 14, 2025
February 2025
February 5, 2025
Housing Unit #3
Programs and Services building
Warehouse
February 19, 2025
Housing Unit #3
February 19, 2025
Administration
February 19, 2025
Programs and Services building
March 2025
March 5, 2025
Housing Units
Administration building
Warehouse
March 19, 2025
Housing Unit 1
Housing Unit 2
Administration building utility work
Warehouse building office space
April 2025
April 7, 2025
Housing Unit 2
Housing Unit 3
Visit room
Warehouse Interior
Administration building
April 16, 2025
Housing Unit 3 view of dayroom from tier
Housing Unit 3 Tier
Housing Unit 2 lower level
Housing Unit 1 Detention doors
Courtyard
Programs and Services building
Visitation
Warehouse Interior
Administration Exterior
April 30, 2025
Administration Building
Housing Unit 1 interior
Housing Unit 2
Housing Unit 3 upper tier
Vehicle sally port area
May 2025
May 14, 2025
Administration building
Visitation area
Housing Unit 1
Housing Unit 2
Programs and Services building
May 28, 2025
June 2025
June 11, 2025
Housing Unit1
Housing Unit 2
Administration hallway
Courtyard
June 25, 2025
Programs and Services Building exterior
A view of the breakdown area inside of receiving.
A view of the second tier deck in Housing Unit #1 which is medium housing.
A view from the tier in Housing Unit 1 (medium).
A view of the second tier cells that are being erected in Housing Unit 2 and Housing Unit 3 (minimum housing).
July 2025
July 9, 2025
Administration building leading to control room and sally port
Housing Unit 1